Project Management Office
Define and develop a strategic project management office by facilitating, and developing tools and processes for the portfolio management process.
Develop a Portfolio management process to prioritize and rank capital projects in the portfolio.
Benchmark systems and implementation of PRISM G2 and PRIMAVERA P6 EPPM.
Developing Project Management best practices: this includes organizational process assets, standardized procedures and establishing project management practices for all departments in the organization.
Defining the Project Management Methodology.
Scope review to align expectations with the redesign and rebuilding of component parts or entire furnace systems to take advantage of the latest, most efficient furnace designs.
MTOs, PFD review to align the estimate with the maximum cost to spend.
Project document Controls.
Project Estimate review.
Project schedule review
Project Cost set-up
Project Cost $230M CAD, duration 2 years.
Replacement one of two existing potash rail dumper receiving and conveyor systems located in Canada.
Cost Controls: development of processes, implementation and monitoring.
Use of Primavera P6 EPPM with Dashboard for forecasting and reporting.
Project document Controls.
Project Estimate review.
Staffing plan elaboration and management.
Package close-out.
Project Cost $300M CAD - Duration: 2 years.
Pre-feasibility and Feasibility StudyA 5,200 metre long tailings discharge, with a 40 centimetre thick reinforced concrete liner.
Review of the cost estimate basis, aligned with AACE Class 4.
Value Engineering ideas generated.
Drill down into WBS, cost structure to highlight high-priority areas for additional review.
Validation of idea assessed (value potential, risk).
Project Cost $180M CAD, 2 Years.
Scoping Study - PFS and FS StudyRevisiting the project scope and objectives and ensuring the master incorporates all necessary activities.
Validation of logics and structure, including dependencies and constraints, to confirm feasibility
Application of the baseline Execution Index with a score of 0.97
Estimate Breakdown structure Marked up PFD’s
Contingency Deterministic Evaluation for option
Schedule elaboration
$2B CAD, 5 Years